Value stream mapping for job shops

Think takt times and value stream maps don’t apply to job shops? Think again. LАвтор/iStock/Getty Images Plus

I’ve worked on lean manufacturing initiatives at more than 300 companies, most of them job shops, and over the years I’ve heard a familiar refrain: We are not Toyota. My response is: “Good! That would be boring!”

Many job shops have studied the Toyota production system. They appreciate its benefits but also question the applicability of one-piece flow in a high-mix, low-volume environment. And rightly so.

I count about 150 tools and techniques in what has evolved into a set of continuous improvement processes universally titled “lean manufacturing.” One tool is value stream mapping (VSM), which aims to create a visual representation of a product or service flow. It identifies where value is being generated and where energy, labor, material, or any other resource is being expended without any value being generated. Waste in all its forms can be more easily identified (and then eliminated) with VSM.

Toyota manager Taiichi Ohno and engineer Shigeo Shingo identified seven primary forms of waste: transportation, overproduction, motion, overprocessing, waiting, defects, and excess inventory. VSM helps visualize where and when various forms of waste are generated.

Because of the nearly unlimited number of customers, product types, and part complexities found within a job shop, applying traditional tools like kanban (make or move signals) and takt time (manufacturing rhythm) can be difficult. Similar challenges apply to VSM.

Toyota makes a limited number of models of a single product type (automobiles). In contrast, a job shop might manufacture medical products, aerospace components, transportation equipment, and one-of-a-kind agricultural products all at the same time. To further complicate the process, make-to-order shops often act as research and development for their customers, helping to develop manufacturable designs for components that may never see a repeat order. The differences between job shops and OEMs are obvious and significant, and they require a significantly different set of VSM tools.

A Review of the Lean Toolbox

First, let’s review several principal tools in the lean manufacturing toolbox. First is the product-quantity-routing (PQR) analysis, which basically answers the following question: “What do we make, how many do we make, and what processes are required to make it?” Takt time defines how often a product, unit, or service is required by your process, like producing one product every minute. In a job shop, of course, all products can have different processing times, and the takt time calculations need to account for this fact (more on this later).

Both the PQR and takt time analysis help build the VSM, long used in OEM environments. The challenge is to have a flexible, dynamic method that job shops can use when the workload changes by the day, sometimes by the hour.

Another lean tool is line balancing. This was first used in the automotive industry by Henry Ford, who had the luxury of making one type of product that allowed work to be divided equally among the appropriate number of workers. Line balancing is much more complex in a job shop, but it’s not impossible. I will demonstrate how a dynamic planning tool can help you know exactly how many operators are needed and where they are needed, in real time.

Standard work is the result of line balancing. Each operator needs to know clearly what their assignment is during each takt time (manufacturing cycle). This is difficult to do using traditional VSM because most mapping methods are static. Job shop workers need a flexible, easy-to-use, dynamic tool for planning their day.

FIGURE 1. Highly oversimplified, these are the process steps required to make a Ford Model A.

All this helps build an optimal facility layout, which is crucial to maintaining a flexible workforce and environment. People need to be able to quickly move to the work when the workload moves from one process to another.

A Deep Dive Into the PQR

Creating a PQR analysis is the first step in transforming a value stream. Knowing what you make, how many, and how you make them will determine all aspects of your VSM. You cannot identify takt time or standard work without knowing how the product is processed through your facility.

Imagine you work for Henry Ford and you need to produce 100 Model As. The Model A is the product (P); 100 is the quantity (Q). Pretty simple so far. The routing (R, or required processes) is a little more complicated. A highly simplified PQR chart for Ford’s production plan might look like Figure 1. The time required to assemble the frame, engine, and so forth will be gathered during the value stream observation. For now, it is just important to identify the required process steps.

The Model A will always require an engine, transmission, and body panels. Parts made in job shops may not require or use all the same processes. Some processes may run only occasionally for special jobs, yet the team still needs access to them.

Imagine you work in a sheet metal job shop that, for the sake of simplicity, makes only two products. Figure 2 shows two different process routings. Part 1 requires welding; Part 2 doesn’t. Part 2 requires shearing and painting while Part 1 doesn’t.

Flow is not consistent. While this example shows the mix as 50%-50%, tomorrow the mix might be 80%-20%. This makes it hard to plan where the labor should be distributed and where equipment should be positioned to minimize distance traveled, motion, and waiting.