PKM1 / Royalty-free / Getty Images
Made in Japan. The phrase meant cheap, disposable, and low quality in the 1950s and 60s. Today, it often implies a product is made with exceptional quality. Much of Japan’s transformation is attributed to individuals like Taiichio Ohno, who in 1943 joined Toyota, where he became known as the father of the Toyota Production System and, eventually, a legend in the realm of lean manufacturing. Legend has it that he’d coach department managers to develop “eyes, ears, and a nose” for the seven types of waste: transportation, inventory, motion, waiting, overproduction, overprocessing, and defects. To this end, he would take each department manager to a central location in his department, draw a circle on the floor with chalk, and order the manager to stand within it and observe.
Ohno would then leave for an hour or more, and upon his return, ask the manager (still standing in the circle), “What have you seen?” The nervous manager might say something like, “I saw people working.” Ohno would shake his head and say, “You are not seeing! Keep watching.” Another hour or so would expire. This process would repeat itself until the manager’s reply satisfied Ohno. “Those parts over there have not moved in the last hour. People are busy, but they are just handling and rehandling components.” Ohno probably responded, “Now you are seeing it. Well done! What are we going to do about it?”
Viewed through the lens of 2023 cultural norms, the technique might be considered condescending or demeaning, but you cannot argue with the results. Learning to see waste is step one. You cannot eliminate what you cannot see.
After serving as a manufacturing consultant for over 30 years, working with over 350 companies and facilitating over 1,000 kaizen project teams, I can tell you that there is waste in every process. It’s shocking to most managers when, after direct observation, they realize their teams are operating within a process having significant nonvalue-adding activity, often between 25% and 30%. If they could eliminate the wasted motion, unnecessary waiting, repetitive stacking and unstacking, counting, moving, damage from handling parts unnecessarily, miscommunication between departments, wasted space covered by inventory, and countless other factors, they theoretically could manage their businesses with labor costs that are 25% to 30% lower. More positively speaking, they could produce and sell 25% to 30% more product with the same staffing levels.
The Cellular Sheet Metal Shop
This is not just a dream scenario. I grew up in a precision sheet metal job shop and experienced a Toyota-like transformation firsthand. In the early 1980s, our largest customer, Tektronix, demanded that we deliver weekly batches of 150 mainframe computer cabinets instead of the 600 per month lot sizes we were used to. They had heard about Toyota’s JIT approach, and Tektronix demanded all their suppliers adopt it.
Our assembly department quickly adapted to the change. Our fabrication department continued to punch, form, and insert hardware for 600 units in a batch (to minimize setup time). We assumed that we had met the customer’s expectations. But shortly thereafter, we were informed that the goal was not just to assemble cabinets 150 at a time, but to fabricate and assemble 150 each week. “And oh, by the way, at some point we will want you to fabricate and deliver 30 per day!”
How could we possibly be expected to set up machines for dozens of complex parts 20 times each month? After all, we had nearly 100 other customers to satisfy. At the time, we had three turret punches, five press brakes, and half a dozen hardware machines.
We peeled off one turret, two press brakes, and a hardware machine, then added a spot welder and a small assembly area. These mild steel parts also needed to be plated, so we had to coordinate with our plating vendor to turn around 30 units daily (handled each day by their second shift) so that we could assemble each day’s fabricated parts beginning the very next morning. It was as if the parts never left our shop. When there was no need for outside processing, we tied fabrication and assembly processes directly together.
Careful value stream mapping (VSM) allowed us to determine the best sequence in which to punch and form the components. Step two was to determine a manufacturing rhythm or takt—that is, the available time divided by demand. Knowing our takt time would allow us to determine how many people, how many pieces of equipment, and how much space would be required.
Our team had 36 hours available to produce each week (accounting for break times and planned downtimes). We needed to produce 150 units per week, which, according to takt time, required us to fabricate and assemble one mainframe computer cabinet every 14.4 minutes (36 hours per week × 60 minutes per hour divided by 150 units = 14.4 minutes per unit). If there were 25 minutes of forming in each unit, then (25/14.4 = 1.74, round up to 2) we would need two press brakes and two press brake operators.
FIGURE 1. The team at the fab shop Gary Conner worked for during the early 1980s. After going cellular, the company went from 70 to 270 people within just a few years.
We also balanced cycle times between operations. We did this by reviewing operator and machine cycle time data gathered during VSM. This helped us establish standard work, or the assignments each person on the team must perform to maintain takt time and smooth workflow. If the total average cycle time to process a unit is 100 minutes, and the takt time is 14.4 minutes, then we need 6.9 team members (100/14.4 = 6.9). We try to avoid loading people more than 85%, so we rounded this up to 8.