Launching a fleet revival at Seaspan shipyard

Progress is made on the Joint Support Ship at the Vancouver Shipyard in May 2023. Seaspan

Streamlining operations in any shop can be a challenge, but when you’re part of a large shipbuilding operation, determining where to find efficiencies and how to execute them is particularly difficult. However, Seaspan Vancouver Shipyards, North Vancouver, B.C., has managed to find smart methods for project staging and has invested in automation where it offers its operations the best return on investment.

National Shipbuilding Strategy Basics

The work that Seaspan is doing at its Vancouver Shipyards is part of the National Shipbuilding Strategy (NSS), which was launched in June 2010. The NSS is a long-term, multibillion-dollar commitment to renew Canada’s federal fleet. It involves three shipyards: Seaspan, which is building a variety of noncombat vessels; Irving, which is constructing combat vessels; and Chantier Davie, which has built a number of icebreakers.

The purpose of the NSS is to help build and maintain an effective federal fleet for maritime security and services while maximizing economic benefits across the country. It is designed to prevent the typical boom and bust cycle that characterizes the traditional approach to shipbuilding.

At a presentation at Metalworking & Manufacturing Expo in Langley, B.C., last year, Dan Southern, director of workforce development at Vancouver Shipyards, showed the audience how the company’s scheduled build program will maintain work on new ships past 2040.

Seaspan’s Role and Progress

Three vessels from the offshore fisheries science vessels project have already been brought into service from Seaspan’s operations. The first vessel, CCGS [Canadian Coast Guard Ship] Sir John Franklin, entered service in June 2019 followed by the second ship, CCGS Capt. Jacques Cartier, in December 2019. The final ship, CCGS John Cabot, was presented to the coast guard in October 2020.

Although these were successful launches, strategically it was important for Seaspan to continue to invest in its value stream to improve efficiencies in its processes to keep future projects on track. Throughout 2021 and 2022, the company invested more than $27 million to increase its capability and capacity. New construction work has benefitted from these investments in technology and infrastructure.

In 2023, multiple ships were under construction at Seaspan Shipyards. The first Joint Support Ship (JSS) that the company is building for the Royal Canadian Navy is “fully consolidated,” Southern noted, and the second JSS began construction in May. Significant work also has been completed on an offshore oceanographic science vessel (OSSV) for the Canadian Coast Guard.

Corey Lutes, director of manufacturing at Seaspan Shipyards, noted that “the best shipyards in the world will produce maybe 60 hulls a year.” But working on the NSS is a different proposition altogether.

“The programs we are working on for our customer are quite bespoke, very mission-specific to what the [Canadian] Navy and Coast Guard need,” he noted. “There are a lot of unique details that add to the complexity and therefore add to the overall cycle time.”

Seaspan By the Numbers Three full-service shipyards in North Vancouver and Victoria 3,600 employees. First class of large vessels delivered under the NSS The commercial repair and overhaul of one ship per week First liquefied natural gas conversion in North America $2.1 billion in contracts awarded to more than 700 Canadian suppliers NSS contribution of $2.6 billion to Canada’s GDP, 2012-2021

To reduce cycle times and improve the overall takt time, Seaspan breaks down the ships into smaller components to focus on how to improve the overall takt time of those smaller components to ultimately build the ship faster.

The subassembly shop includes this automated Suprarex gantry plasma cutting table, robotic profile cutting, an automated welding T-beam line, and a micropanel robotic welding line. The typical plate size processed on this table is 40 by 10 ft., and the bars are 40 ft. long. Seaspan

Demanding Designs

The design starts by identifying the client needs regarding ship missions and operability areas, then defining the ship’s main dimensions, ship hull form, general arrangement, and all associated systems (propulsion, piping, HVAC, electrical, and dedicated missions system). All of these are integrated in a 3D model environment from which the production drawings are extracted and provided to production.

“Real estate is at a premium, so design maturity is critical from the start,” said Lutes. “It usually takes about a year to develop this sort of model. Everything from structure, piping systems, electrical, cable tray, and major equipment is included in the model. We minimize as much change as possible prior to beginning construction.”

The ship’s design dictates how its smaller components can be broken out for fabrication. One block is typically a full beam breadth, ranging from 20 to 24 m by 12 m long.

“Construction generally has the blocks inverted to promote effective execution of the work down-hand rather than doing everything overhead,” said Lutes. “It’s much more ergonomic and efficient.”

Sequencing is key.

“As the product gets bigger and we see it through the yard, we end up becoming very reliant on our workforce,” noted Lutes. “We try to automate as much as possible at the earlier stages of construction. But ultimately, given the size and scale of the project, we are still very dependent on the skilled labor force. So there’s also a lot of emphasis on how to get our labor force to be more efficient and effective as well.”