The hidden cost drivers and overlooked details of structural steel fabrication

FIGURE 1. This complex, cover-plated, wide-flange column has extensive bracing, designed for blast resistance. All this work adds significant cost, both for labor in the shop and in the field. Sometimes such complexity just isn’t avoidable, but the cost of that complexity needs to be factored into the job.

Tim Bradshaw is all about giving shop tours, especially to structural engineers. As vice president of project delivery at Owen Steel Co. , Columbia, S.C., Bradshaw has been designing and fabricating structural steel his entire career. For more than 25 years, he has worked as a professional engineer and manager in the industry. He knows when metal fits together well—and when it doesn’t.

“Three factors influence cost in structural steel. First is the cost of material, second is the shop labor cost, and third is the erection cost. A long-held rule of thumb has held that each comprises about a third of overall cost. That is, a job’s cost is one-third material, one-third shop labor, and one-third erection.”

Bradshaw made this statement in March 2022 during a presentation he gave in Denver at NASCC: The Steel Conference, organized by the American Institute of Steel Construction (AISC). He added that the rule fluctuates over time with changing material and labor costs. Sometimes, however, the rule swings out of balance because of certain design choices the engineer of record (EOR) made or factors the EOR simply overlooked.

Of all the sectors in metal fabrication, structural steel fabrication stands apart. The construction supply chain is less of a chain and more of a complex web of interconnected parties. A structural steel fabricator can be just a cog in the wheel, fabricating what it’s given, or it can be an active communicator, showing the EOR (and anyone else) what truly drives costs and efficiencies on the fab shop floor (see Figures 1 and 2). It’s why Bradshaw, who serves on three AISC committees, always welcomes the chance to give a shop tour. In fact, his NASCC presentation could be seen as a virtual shop tour of sorts, during which he pointed out various factors that throw the costing rule of thumb off-kilter.

Never Look at Weight in Isolation

Bradshaw pointed to a simple beam with straightforward connections. “In this case, less weight really does equal less cost. It’s a simple beam, there’s not a lot of shop labor, and it’s not expensive to install in the field.”

He then pointed to a spandrel beam (edge beam constructed along the exterior wall of each floor) with a long, cantilevered edge. Its lightweight construction looks great in isolation, but that light weight also requires steel reinforcement. “You just quadrupled the weight of the beam because of all the reinforcing steel you need to add to that beam to handle the cantilevered edge. It might have been better to make the beam a little heavier or use a tubular section for your spandrel, or to not have that long cantilevered edge.”

He then pointed to some shop drawings involving stiffeners and doublers. Depending on the design, lighter columns might require more robust stiffeners and doublers, and welding them isn’t free. In his presentation, he pointed to a lightweight W14 × 159 column with a 6-in.doubler and a W14 × 342 with a ½-in. doubler. From a pure material cost perspective, W14 × 159 seems the way to go, until you look at all the welding those doublers require. The 6-in. doubler plates on W14 × 159 increased overall weld volume by 72 times. Much of this has to do with geometry; a full-penetration weld is essentially a triangle, and its volume increases exponentially with its size. With increased weld volume comes multiple weld passes and more costs.

“In this case, it might be less expensive to go with a W14 × 342 in place of that W14 × 159 column,” he said, “especially if you’re making moment connections at multiple levels coming in from multiple directions.”

Questions About Connections

Detailing, connection engineering, fabrication—sometimes all three are done under one roof; other times they’re done by different firms. Regardless, open communication is key (see Figure 3).

FIGURE 2.A lightweight beam might require web reinforcements like this—another factor that affects weight versus cost considerations.

Some fabricators, especially those with plenty of punching and drilling equipment, are set up to do bolted work very efficiently; others weld efficiently; some excel at both. Of course, engineers often develop drawings without knowing which fabricator will perform the work. “If you don’t know whether the fabricator will be set up to do welded work, bolted work, or both, try to allow for either bolted or welded connections.”

Single-sided connections work best for the erector. “You of course can’t use a single-sided connection all the time, but use as many as you can,” he said. “There’s a lot of research in the latest Steel Construction Manual [published by AISC] about not only standard shear tabs but also extended shear tabs. [Using these] can go a long way, especially if you’re connecting to the web of a column, or if you’re coping into a web of a girder that has a really wide flange. If you can use an extended shear tab connection, you don’t have to worry about coping the beam as much.”

He added that when it comes to design loads, specifics matter. When given a specific load requirement—this W12 has a minimum connection load of 20 kips; for that W14, it’s 24 kips—connection engineers check every connection against that load.

Sometimes, though, connection engineers are just given a tabulated list that shows the minimum number of a specific type and size of bolt. “That doesn’t tell us much from a connection standpoint,” he said. “We can give you a W16 with four bolts in it, but what does that mean for block shear? What does that mean for bolt bearing? What does that mean for bending on the net section? We really need specific load information in some form.”

Weld Specifics Matter