Better structural fabrication starts with good information

Urupong/iStock/Getty Images Plus

When can we get the shop drawings? Kerri Olsen has heard that question countless times during the first meeting of the fabricator, steel detailer, and client (usually a representative from the general contractor). She’s founder and principal of Steel Advice, an estimating and project management firm in Shelton, Wash., and she’s also the current acting president of the National Institute of Steel Detailing (NISD). To Olsen, that’s the wrong question for a fabricator to ask—especially at an initial meeting.

“In my mind, the first question should always be, ‘What information is yet needed to enable the start of steel detailing?’ If that’s the first time they’ve heard the question, don’t let it be the last time.”

Olsen said this during a March 2022 seminar at NASCC: The Steel Conference, hosted in Denver by the American Institute of Steel Construction (AISC). Her presentation delved into one of the most time-consuming elements of a construction project: requests for information, or RFIs.

Focus on the Root Cause

Olsen offers both estimating and project management services. When she receives a job, she first thoroughly reviews contract drawings, specifications, and anticipated delivery dates. “The next thing I do is mark the contract drawings where I see missing information,” she said. “If I’m the estimator on the job, I already have an idea of what was not included in the scope-of-work items. I’m able to hit the ground running. But if I’m coming in blind, I’ll go through page by page and mark up what I’m going to need to get started.”

She then writes an introductory letter detailing the missing elements and holds a meeting with the fabricator. This all happens before meeting with the steel detailer.

“Fabricator project managers should do what they can to completely know a job,” she said. “They should preview the job with the estimators, people who’ve had their heads in the job and know what the problem areas are. [The estimator and project manager] should work together in identifying all critical elevations and dimensions that are shown and are missing. And they need to completely review the scope of the work and talk about specific items and quantities. Just because it’s only shown as a detail once doesn’t mean there aren’t 50,000 of them in a job.”

Once the project manager and estimator are on the same page, they bring detailing into the picture. After the initial detailer bid—which, again, involves all expected items, the complete scope of the work, and timelines—steel detailing is brought into the project and the meetings commence.

At this first meeting, the estimator, project manager, and steel detailer start developing a list of missing information—all before the formal RFI process begins. The idea is to uncover most missing information as early as possible, abiding by best practices as defined by AISC and NISD codes.

Specifics matter here. Yes, job contracts say all parties abide by AISC and NISD best practices, but what do these standards actually say? Olsen pointed to a section in the NISD standard that states, “The structural design documents shall clearly show or note the work that is to be performed and shall give the following information with sufficient dimensions to accurately convey the quantity and complexity of the structural steel to be fabricated.” The standard follows with a long list of details, the first one being “the size, section, material grade, and location of all members.”

She also said that just scaling up CAD drawings to determine dimensions “is not an accepted practice for detailing the approval documents,” adding that this has to do with information responsibility and accountability. Per best practice, as-received design documents must contain all required dimensions.

Information Responsibility

“Everything we do when we start a job has to keep pointing back to the root cause,” Olsen explained, “and the root cause of most of our problems is that the design was incomplete. The reality is that contract drawings almost always aren’t workable, and many feel, ‘Well, why not just go ahead and detail the job, and put clouds [in the PDF markup] with questions on the shop detail and erection drawings, and then send them for approval?’ That’s not a good process.”

Doing that shifts information responsibility. Best practice assumes that detailers release drawings that are shop-ready, with all expected problems addressed and questions answered. Olsen’s message to detailers: “When you submit drawings for approval, you’ve admitted to the world that these drawings are workable. Now, you’ve made yourself responsible for whatever timeline is involved. Ideally, you should never submit drawings for approval until they are complete, when you have all questions answered and you’re good to go. Even though you’re just in the approval stage, you could fabricate off these drawings now because they’re that complete. That’s what we want.”

Weekly Information Notices

Of course, detailers can’t simply state, “These drawings are unworkable, now fix them,” then just leave it at that until someone notices nothing is moving forward. Fabricators need to order the steel, after all, and projects still have expected completion dates. Here’s where Olsen’s weekly project information notices come into play.

“I send a descriptive letter,” she said, “not pages and pages of data. I condense everything into short, informative sentences. If I have to use a spreadsheet, I will, but I try not to. The weekly letters describe the current job status, what’s been resolved, and what is needed to continue.”