Perfecting the job shop schedule in metal manufacturing

Anatolii Shcherbatiuk / iStock / Getty Images Plus

Fabricators have invested in evermore powerful fiber lasers, press brakes with automated tool changes, expanded welding capability, powder coating—the list of capex goes on, and yet on-time delivery performance remains stubbornly mediocre. According to the annual “Financial Ratios & Operational Benchmarking Survey,” published by the Fabricators & Manufacturers Association, average on-time delivery has hovered between 77% and 88% for the past decade.

Sure, supply chain challenges have complicated matters as changes from customers and the delivery of material and purchased components becomes more erratic. Acute worker shortages and unexpected absences haven’t helped either. Still, on-time delivery in custom fabrication was mediocre long before the pandemic, and most fabricators have dealt with the skilled labor shortage for years. So, what gives?

A shop sets a schedule and yet doesn’t stick to it. The scramble ensues. Overtime mounts along with frustration. Root causes abound and can be pervasive, reaching every process of the business. Improving matters is a complicated puzzle, and an important piece can involve finding a better way to schedule.

Improvements in Data

Every custom fab shop has its own unique customer mix, so the reasons behind scheduling challenges are too numerous to count, but many of them deal with one key area: a lack of good information. As with anything else, when it comes to scheduling, garbage in, garbage out.

“We’ve seen over the years that companies are getting better, data-wise,” said Dan Hahn, vice president of ATS Lean Scheduling International, a provider of advance planning & scheduling (APS) software in Bradenton, Fla. “That said, data still is one of our primary issues. If we work with a manufacturer with good, clean data, it’s a godsend.

“Lately, we’ve seen a lot of issues with people and materials, and shops have a hard time maintaining a consistent group of talented people,” Hahn continued. “They’re now looking to us [APS software providers] to give them the ability to reschedule, reshuffle, and react to change.”

Data collection remains at the heart of the issue. Some of it might be housed on clunky software in desperate need of an update. And even with the slickest of software, garbage in, garbage out still applies. It’s tough to schedule based on available capacity when a manufacturer doesn’t know what available capacity really is.

Imagine a press brake operator clocks in on a specific bending job, then realizes he needs to fetch tooling from the toolroom across the factory floor. So, he walks, retrieves tooling, sets up and runs the job, then finally clocks out from the job. The system says the job took 30 minutes, but in truth, it took the operator less than half the time to set up the machine and run parts. The problem might be easy to spot if that job comes up on a consistent basis. (That’s what going to Gemba is all about, after all.) But in a high-product-mix operation, this and numerous other wasteful tasks can stay hidden and unnoticed.

Direct machine connection and monitoring can help here. Imagine the same scenario, only this time the machine itself automatically reports actual uptime and setup time for each job, as well as the personnel requirements: the operator, fork truck driver or material handler, perhaps a dedicated setup person. That data quickly reveals improvements, like having tools at the point of use. More broadly, the connection reveals what’s actually going on during production.

Competing on Differences

“I’ll be honest, APS is difficult to implement,” said Mike Liddell, founder of Lean Scheduling International and author of the book “The Little Blue Book on Scheduling,” a tome that spells out scheduling challenges for the high-product-mix shop. “Every company is different, and that difference is their competitive advantage. It’s about being able to incorporate that difference into an APS.”

FIGURE 1. When blue runs first, it takes 11 days to process three orders.

Hahn added, “Because every manufacturer is different, with different processes, we need to be able to mold the [APS] tool to make those processes better.”

Two precision sheet metal shops might have similar machines, but their customers are different. Some might demand the shop hold some level of finished goods inventory. Other customers (lawn and garden, for instance) might have highly seasonal demand, meaning the schedule needs to account for that demand variability. Still other customers have certain jobs that make a fabricator highly reliant on outside services and purchased components—yet more variables the APS needs to account for.

“One job shop might produce 20,000 parts in a batch, which can be easy to schedule since you have the same machines doing the same parts over and over again,” Hahn said. “Then you have those who run very small batches, which means you need to focus on changeovers and how best to process the material through the routing.”

Such varying demand drives different strategies when it comes to WIP. Some shops will run certain subcomponents ahead to maintain a parts supermarket that downstream operations can draw from. Others simply can’t produce ahead because they don’t know which parts will be needed.

This in turn drives different order release and nesting strategies at the punch and laser. Does it make sense to cut ahead in the schedule to fill a nest? Alternatively, should the shop manage remnants or just deal with excessive scrap? Also, are various jobs grouped together dynamically on a single sheet, or are certain cutting resources dedicated to only certain customers? What about jobs requiring sheets of different grades and thicknesses? How should the subcomponents be dispersed and sequenced among the shop’s cutting work centers?