Estimating basics and quoting jobs in custom metal fabrication

erhui1979 / DigitalVision Vectors / Getty Images

In an era of rising costs from labor shortages and supply chain challenges, timely access to data is essential. Static spreadsheets used for estimating and tracking costs need to be replaced by dynamic data management, such as enterprise resource planning systems that incorporate historical, tribal knowledge with the collection and analysis of current data. The goal is to generate consistent estimates and provide profitable, competitive pricing.

Estimating fundamentals matter, especially now. Numerous factors influence the cost to produce parts, and understanding the basics of shop rates and sell rates is critical to determine a sell price that is both competitive and profitable.

How to Calculate the Shop Rate

Shop rates are the costs incurred for the production of parts on an hourly basis. To determine shop rates, first identify your direct hourly labor rates, your fixed overhead costs, and your variable overhead costs.

Direct hourly labor rates are the easiest to establish. They’re simply based on the actual hourly wage paid to employees. To determine the direct hourly labor rate for each production department, add the hourly wage rate for each department employee and then divide that by the total number of employees. This gives you the average hourly rate.

Most companies will then round that up. If your average rate were $18.33 per hour, you might round that to $18.50 or $19.00. Be sure to calculate the direct hourly labor rate for each production department, each of which has varying degrees of expertise among trained employees.

You also might consider identifying a rate for setup. Some machines may require more experienced employees for setup, but once they produce the first article, a less experienced employee can run the parts.

You could even establish direct hourly labor rates based on job type, such as prototype versus production or standard run versus expedited. Typically, a more experienced employee will produce prototypes, and a shop will charge higher rates for expedited production.

Overhead rates are more difficult to establish. Some just establish a single overhead rate for the facility, while others develop rates for each production department. After all, the costs behind every process—cutting, bending, deburring, machining, welding, or other anything else—can vary. Some machines may be fully depreciated while other machines are brand new and are just starting to be depreciated or have a lease payment each month. Power consumption can vary as well, and some equipment may require more maintenance.

Developing overhead rates for each production department lets you see the true cost of running the operation and allows you to be more competitive in your pricing. To develop overhead rates by production department, you need to look at both fixed and variable overhead expenses.

Fixed overhead costs are incurred whether the facility is up and running or shut down. Examples would be rent, equipment leases, utilities, and depreciation. Calculating these for the entire facility is straightforward; determining fixed overhead costs for each production department is a little more complex.

FIGURE 1. The sell price incorporates the sell rate, material and hardware, and outside processing. In this example, the sell rate includes shop rate overhead, direct labor, and profit, but some also incorporate operational overhead that includes expenses like sales, marketing, accounting, and administration.

Using the most recent 12 months of data, you may allocate costs to each production department based on square footage (rent, utilities) or equipment costs (equipment leases and/or depreciation). Once you have the total costs allocated to each production department, determine the hourly cost by dividing the total by the estimated productive hours for the next 12 months. This will give you the fixed overhead costs by hour for each production department.

Variable overhead costs are directly related to the production of revenue-generating parts. Examples would be consumables such as welding gases, welding wire or rod, safety equipment, and indirect labor. These expenses vary with increases or decreases in production.

Again, using data from the past 12 months, you can allocate costs to the corresponding production department. Because we’re in an inflationary period, you’ll want to increase these total costs based on expected increases over the next 12 months. You then divide a department’s total costs by the estimated productive hours for the next 12 months, giving you the variable overhead costs by hour for each production department.

Estimated productive hours is the time equipment is expected to produce revenue-generating parts. A one-shift operation, eight hours per day, five days per week, has 2,080 hours worked in a year. Of course, employees don’t work for 2,080 hours. They take breaks, as required by law, they go on vacation and sick leave, and they have company holidays. And sometimes an employee is out, leaving no one available to operate a machine. Additionally, some departments may not be fully utilized over the course of 12 months.

Once you determine the percentage of time a department will be productive, multiply that percentage by the 2,080 hours (or more, if you’re running multiple shifts) to determine the estimated productive hours for that department. So, a department that works 80% of the time would have 1,664 estimated productive hours a year (2,080 × 0.80).

For production departments with multiple machines, estimated productive hours would incorporate the sum of all of them. Say you have three lasers in your cutting department, and the estimated productive hours for each is 1,664. So, the total productive hours per year for the department would be 1,664 × 3, or 4,992 hours.